MUNSHIGANJ: The 13th span (super structure) of the 6.15-kilometre Padma Bridge was installed between 14 and 15 number pillars at Mawa point making 1950 meters of the bridge visible.
The installation work finished around 09:55 am on Saturday (May 25).
The 13th span was erected after 18 days of the 12th span.
The 1st span was set up on September 30, 2017. Two-story Padma Bridge is being built for multipurpose. Concrete and still are main ingredients of the bridge.
BDST: 1141 HRS, MAY 25, 2019